Mining and quarries · Mining and resources
Mt Arthur Coal Mine - Exploration
PMB 8 Muswellbrook New South Wales Australia 2333 · Muswellbrook Shire · New South Wales
ApprovedMP06_0040No EPBC referral
Where the approval stands
- 0.3 km
- To a 132 kV line
- StatePart 3A major project, MP06_0040
Approved. Minister for Planning. Lodged 13 August 2019. Decided 20 September 2006.
View record
Constraints
Public maps, asked when this page opens · within 5 kmChecking national and NSW maps…
Facts and sources
- Location
- PMB 8 Muswellbrook New South Wales Australia 2333, Muswellbrook Shire, New South Wales
- Owner
- Not published
- Contractors
- Not named in a public source yet
- Value
- Not published
- Distance to the grid
- 0.3 km to a 500 kV line. 8.2 km to Bayswater substation (500 kV).Straight line from the mapped site to operational lines and substations of 132 kV or more.
- Last activity
- 13 August 2019
- NSW Major Projects portalLicence: CC BY 4.0. Retrieved 22 October 2026.
- Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.