Agriculture · Industrial and waste

Moira Feedlot

Unit 22B, Level 2, 12-18 Tyron Road Lindfield New South Wales Australia 2070 · Murray River · New South Wales

ApprovedMP05_0081No EPBC referral
-35.9471, 144.8726Open the map
© OpenStreetMap · OpenMapTiles · OpenFreeMap

Where the approval stands

45 km
To a 132 kV line
  • StatePart 3A major project, MP05_0081

    Approved. Minister for Planning. Lodged 13 August 2019. Decided 23 May 2006.

    View record

Constraints

Public maps, asked when this page opens · within 5 km

Checking national and NSW maps…

Facts and sources

Location
Unit 22B, Level 2, 12-18 Tyron Road Lindfield New South Wales Australia 2070, Murray River, New South Wales
Owner
Not published
Contractors
Not named in a public source yet
Value
Not published
Distance to the grid
45 km to a 132 kV line. 60 km to 220 kV. 46 km to Deniliquin 132 substation (132 kV).Straight line from the mapped site to operational lines and substations of 132 kV or more.
Last activity
13 August 2019
  1. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 22 October 2026.
  2. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.

Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.