Housing · Property
Mixed-use development with in-fill affordable housing at 2-6 Pilgrim Avenue and 11-13 Albert Road, Strathfield
2-6 Pilgrim Avenue, 11-13 Albert Road, Stratfield · Strathfield · New South Wales
ApprovedSSD-80432461No EPBC referral
Where the approval stands
How this is worked outDecided 14 months after its first record on the NSW portal. Of the 216 NSW property projects that entered the portal from August 2020 and have been decided, half took 20 months or less.
Decided, 14 months
- $110m
- Capital investment value
- 14 mo
- Time to decision Typical 20 mo
- 221
- Construction jobs
- StateState significant development, SSD-80432461
Approved. NSW Department of Planning. Lodged 26 February 2025. Decided 30 April 2026.
View record
Constraints
Public maps, asked when this page opens · within 5 kmChecking national and NSW maps…
Aust Customs - Container Examinatiion FacilityValue not published2A-4 Edwin Flack Avenue, Sydney Olympic ParkValue not published2A and 2B Australia Avenue, Sydney Olympic Park$207m1 & 2 Murray Rose AvenueValue not publishedBreakfast Point - Blacksmiths' WorkshopValue not publishedBreakfast Point - The PointValue not published
Facts and sources
- Location
- 2-6 Pilgrim Avenue, 11-13 Albert Road, Stratfield, Strathfield, New South Wales
- Owner
- Not published
- Contractors
- Not named in a public source yet
- Value
- $110m, capital investment value
- Jobs
- 221 during construction, 26 once operating
- Last activity
- 30 April 2026
- NSW Major Projects portalLicence: CC BY 4.0. Retrieved 22 October 2026.
- NSW Major Projects documentsCapital investment value stated in the Department's notice of decision. Document: SSD Notice of Decision.pdf. Licence: CC BY 4.0. Retrieved 22 October 2026.
Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.