Melbourne Renewable Energy Hub Side B
Other generation · Plumpton · Victoria
- Capacity
- 200 MW
- To a 132 kV line
- 6.1 km
Overview
Awarded in the Capacity Investment Scheme (CIS Tender 8 - NEM Dispatchable, announced 24 June 2026). 200 MW batter.
- Location
- Plumpton (town centre; the tender results do not give the site), Victoria-37.6619, 144.6616
- Value
- Not published
- Capacity
- 200 MW, with 800 MWh of storage
- Owner
- Equis Australia
- Distance to the grid
- 6.1 km to a 500 kV line. 7.7 km to Sydenham substation (500 kV).Straight line to operational lines and substations of 132 kV or more.
Approval progress
- PlanningNow
- Assessment
- Approved
- Construction
- Operating
Early signals
- 24 June 2026Awarded Commonwealth underwriting in the Capacity Investment SchemeCIS Tender 8, NEM Dispatchable, announced 24 June 2026. 200 MW, 800 MWh.Capacity Investment Scheme. A signal is not a planning approval.Awarded
No state or federal approval is recorded yet. Projects appear here once lodged with the approving authority or referred under the EPBC Act. Get an email when that happens.
Reports on this project
- Project brief, free.
- Project dossier, On enquiry.
- Insights report, On enquiry.
The facts on this page stay free.
What each contains© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the mapSite constraints
Site constraints
Checking national and VIC maps…
Who's involved
- Equis AustraliaOwner
Nearby
- Melton Recycled Water Plant - major mechanical upgrade worksIn planning · $94m5 km
- Building Better TAFE Fund - Melton (New TAFE Campus)Under construction · $55m5 km
- High St Melton Commercial & Retail DevelopmentIn planning6 km
- Melton Renewable Energy Hub, Plumpton, VictoriaApproved6 km
- New Melton HospitalUnder construction · $1.5bn7 km
- Calder Park Drive and Holden Road Level Crossing Removal ProjectApproved8 km
Sources
- Capacity Investment Scheme tender results, DCCEEWPlaced at the centre of its suburb (ABS). Licence: CC BY 4.0. Retrieved 22 November 2026.
- Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.