How this is worked out

Decided 31 months after its first record on the NSW portal. Of the 63 NSW generation and storage projects that entered the portal from August 2020 and have been decided, half took 34 months or less.

Decided, 31 months
Half of 63 comparable cases decided by Nov 2023
$398m
Capital investment value
31 mo
Time to decision
Typical 34 mo
300
Construction jobs
  • StateState significant development, SSD-13137914

    Approved. NSW Department of Planning. Lodged 14 January 2021. Decided 15 August 2023.

    View record

Constraints

Public maps, asked when this page opens · within 5 km

Checking national and NSW maps…

Facts and sources

Location
740 Carrick Road/154 Munro Road, Carrick, Goulburn Mulwaree, New South Wales
Contractors
Not named in a public source yet
Value
$398m, capital investment value
Jobs
300 during construction
Last activity
22 September 2026
  1. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 22 October 2026.
  2. NSW Major Projects documentsCapital investment value stated in the Department's notice of decision, given as an approximate figure. Document: Notice of Decision.pdf. Licence: CC BY 4.0. Retrieved 22 October 2026.