- $130m
- Capital investment value
- 1 km
- To a 132 kV line
- StatePart 3A major project, MP06_0043
Approved. Minister for Planning. Lodged 14 August 2019. Decided 6 July 2006.
View record
Constraints
Public maps, asked when this page opens · within 5 kmChecking national and NSW maps…
Mixed Use Development and Rezoning at 251-257 Maroubra Road, Maroubra$80mBanksmeadow Waste FacilityValue not publishedMixed use development at 32-34 Blenheim St$62mBuilding D14 Redevelopment$118mAffordable Housing Development - Botany Road, MascotValue not publishedAlexandria Health Centre Concept Proposal$84m
Facts and sources
- Location
- Anzac Parade Malabar Sydney New South Wales Australia, Randwick City, New South Wales
- Contractors
- Not named in a public source yet
- Value
- $130m, capital investment value
- Distance to the grid
- 1 km to a 132 kV line. 8.2 km to 330 kV. 1.6 km to Bunnerong substation (132 kV).Straight line from the mapped site to operational lines and substations of 132 kV or more.
- Last activity
- 14 August 2019
- NSW Major Projects portalLicence: CC BY 4.0. Retrieved 22 October 2026.
- NSW Major Projects documentsCapital investment value stated in the Department's assessment report. Document: Director-General's Assessment Report.pdf. Licence: CC BY 4.0. Retrieved 22 October 2026.
- Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.