Expansion of the railyard, including two new bypass tracks, two provisioning tracks, a provisioning facility and a wagon maintenance facility.
- Location
- Queensland-21.4561, 149.2362
- Value
- Not published
- Approving authority
- Queensland Coordinator-General
Approval progress
- Planning
- Assessment
- ApprovedNow
- Construction
- Operating
Coordinated project is the one instrument on record for this project. Later steps appear here as the public registers record them.
- Coordinated project, environmental impact statementQueensland · Queensland Coordinator-GeneralAssessment completed↗
Reports on this project
- Project brief, free.
- Project dossier, On enquiry.
- Insights report, On enquiry.
The facts on this page stay free.
What each contains© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the mapSite constraints
Site constraints
This project runs along a route but is mapped at one point on it, so the screen covers that point only.
Checking national and QLD maps…
Nearby
- Port of Hay Point Dredging ProjectApproved25 km
- Construction of the proposed Mackay Port Access Road – Section 3In planning39 km
- PLEYSTOWE BATTERY ENERGY STORAGE SYSTEMIn planning40 km
- Burrenbring Battery Energy Storage System (BESS)In planning59 km
- Mount Britton Battery Energy Storage SystemIn planning60 km
- Nebo BESS Energy Storage System (Nebo BESS) and Nebo Substation ExpansionIn planning60 km
Sources
- Coordinated projects, the Coordinator-GeneralDeclared a coordinated project under the State Development and Public Works Organisation Act 1971: completed eis, the Coordinator-General's evaluation report issued. The location is the indicative project area published by the Coordinator-General. © State of Queensland. Licence: CC BY 3.0 AU. Retrieved 22 November 2026.
Spotted an error? Tell us.
Get every change to rail projects in QLD, and the firms you follow, in the Monday briefing.