Skip to content
Hunter energy Hub
Other generation · Muswellbrook Shire Council · Muswellbrook Shire Council · New South Wales
- To a 132 kV line
- 15 km
Overview
Supported by the NSW Investment Delivery Authority (renewable energy and energy security). Hunter energy Hub. Not yet on the NSW Major Projects portal.
- Location
- Muswellbrook Shire Council (council area centre; the list names the council, not the site), Muswellbrook Shire Council, New South Wales-32.4880, 150.6984
- Value
- Not published
- Distance to the grid
- 15 km to a 330 kV line. 25 km to Bayswater substation (500 kV).Straight line to operational lines and substations of 132 kV or more.
Approval progress
- PlanningNow
- Assessment
- Approved
- Construction
- Operating
Early signals
- Date not publishedSupported by the Investment Delivery Authority for a faster assessmentListed under renewable energy and energy security. Hunter energy Hub.Investment Delivery Authority. A signal is not a planning approval.Supported
No state or federal approval is recorded yet. Projects appear here once lodged with the approving authority or referred under the EPBC Act. Get an email when that happens.
Reports on this project
- Project brief, free.
- Project dossier, On enquiry.
- Insights report, On enquiry.
The facts on this page stay free.
What each contains© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the mapSite constraints
Site constraints
Checking national and NSW maps…
Nearby
- Dalswinton Sand and Gravel QuarryIn assessment5 km
- Edderton Solar FarmIn planning · $850m12 km
- Myambat Depot - Storage and Distribution ProjectIn planning14 km
- Denman Battery Energy Storage SystemIn assessment · $1.8bn16 km
- Upper Hunter South Solar FarmIn assessment · $163m16 km
- Upper Hunter South Solar FarmWithdrawn16 km
Sources
- Investment Delivery Authority, Investment NSWPlaced at the centre of its council area (ABS). Licence: CC BY 4.0. Retrieved 22 November 2026.
- Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
Spotted an error? Tell us.
Get every change to other generation projects in NSW, and the firms you follow, in the Monday briefing.