Gnarwarre Battery Energy Storage System

Batteries and pumped hydro · Surf Coast · Victoria

To a 132 kV line
18 km

Overview

Applies the Specific Controls Overlay to 189-389 Volum Road, Gnarwarre and introduces the 'Gnarwarre Battery Energy Storage System (BESS) - 189-389 Volum Road, Gnarwarre - Incorporated Document - February 2021' to facilitate the use and development of a 500MWh battery energy storage system (BESS).

Location
Surf Coast (council area centre; the amendment names the council, not the site), Victoria-38.3415, 144.1155
Value
Not published
Approving authority
Victorian Minister for Planning
Distance to the grid
18 km to a 220 kV line. 35 km to Geelong substation (220 kV).Straight line to operational lines and substations of 132 kV or more.

Approval progress

2 approvals on record
  1. Planning
  2. Assessment
  3. ApprovedNowApproved 31 Oct 2022
  • Planning scheme amendment (Surf Coast)Victoria · Victorian Minister for Planning · C135surf
    Lodged, date not published → 9 May 2021
    Approved↗
  • Planning scheme amendment (Surf Coast)Victoria · Victorian Minister for Planning · C142surf
    Lodged, date not published → 31 Oct 2022
    Approved↗

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and VIC maps…
  1. Strathmore Drive Development PlanIn planning15 km
  2. Pettavel Basin Augmentation ProjectApproved18 km
  3. Barwon Heads Road, Lake Road to Lower Duneed Road Upgrade ProjectIn planning26 km
  4. DIDR01 Wetlands, Barwon Heads Road, Armstrong CreekApproved26 km
  5. Barwon Heads Road Upgrade - Stage 2In planning · $318m26 km
  6. Barwon Heads Road Reserve Road to Lower Duneed Road Upgrade ProjectIn planning26 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. Victorian planning scheme amendments, Department of Transport and PlanningAmendment C135surf: Finished, approved, decided 2021-05-09, gazetted 2021-05-28. Retrieved 25 November 2026.
  2. Victorian planning scheme amendments, Department of Transport and PlanningAmendment C142surf: Finished, approved, decided 2022-10-31, gazetted 2022-11-18. Retrieved 25 November 2026.
  3. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.

Spotted an error? Tell us.

Get every change to batteries and pumped hydro projects in VIC, and the firms you follow, in the Monday briefing.