Deer Park

Batteries and pumped hydro · Ravenhall · Victoria

Capacity
275 MW
To a 132 kV line
0.2 km

Overview

Last activity 2026

Awarded in the Capacity Investment Scheme (CIS Tender 3 - NEM Dispatchable). 275 MW (4 hour) battery.

Location
Ravenhall (town centre; the tender results do not give the site), Victoria-37.7733, 144.7367
Value
Not published
Technology
Battery, 275 MW, with 1,100 MWh of storage
Distance to the grid
0.2 km to a 220 kV line. 0.5 km to Deer Park substation (220 kV).Straight line to operational lines and substations of 132 kV or more.

Approval progress

No approval on record
  1. PlanningNow

Early signals

  1. Date not publishedAwarded Commonwealth underwriting in the Capacity Investment SchemeCIS Tender 3, NEM Dispatchable. 275 MW, 1,100 MWh.Capacity Investment Scheme. A signal is not a planning approval.Awarded

No state or federal approval is recorded yet. Projects appear here once lodged with the approving authority or referred under the EPBC Act. Get an email when that happens.

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and VIC maps…

Who's involved

From the registers, certificates and disclosures that name the project
  1. Industrial Subdivision ProjectIn planning1 km
  2. Proposed Sports Pavilion Development, Bon Thomas Reserve, 57A Quinn Street, Deer Park, VictoriaApproved2 km
  3. 489A Robinsons Road TruganinaApproved2 km
  4. Industrial development, 489-555 Robinsons Road, Truganina, VicApproved3 km
  5. Commercial and Industrial Development (Stage 3), Deer Park, VictoriaIn assessment4 km
  6. Residential development 80a and 80b Oakwood Road, Albanvale, VicApproved4 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. Capacity Investment Scheme tender results, DCCEEWPlaced at the centre of its suburb (ABS). Licence: CC BY 4.0. Retrieved 22 November 2026.
  2. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.

Spotted an error? Tell us.

Get every change to batteries and pumped hydro projects in VIC, and the firms you follow, in the Monday briefing.