Water and wastewater · Water and utilities
Cowarra Water Supply Scheme
Forestry Corporation of NSW, Cowarra Access Road, LAKE INNES, NSW 2446 · Port Macquarie-Hastings · New South Wales
ApprovedSSI-57056461No EPBC referral
Where the approval stands
How this is worked outDecided 34 months after its first record on the NSW portal. Of the 510 NSW major projects that entered the portal from August 2020 and have been decided, half took 23 months or less.
Decided, 34 months
- $165m
- Capital investment value
- 34 mo
- Time to decision Typical 23 mo
- StateState significant infrastructure, SSI-57056461
Approved. NSW Department of Planning. Lodged 3 April 2023. Decided 26 January 2026.
View record
Constraints
Public maps, asked when this page opens · within 5 kmChecking national and NSW maps…
Facts and sources
- Location
- Forestry Corporation of NSW, Cowarra Access Road, LAKE INNES, NSW 2446, Port Macquarie-Hastings, New South Wales
- Contractors
- Not named in a public source yet
- Value
- $165m, capital investment value
- Last activity
- 26 January 2026
- NSW Major Projects portalLicence: CC BY 4.0. Retrieved 22 October 2026.
- NSW Major Projects documentsCapital investment value stated in the Department's assessment report. Document: SSD-SSI Assessment Report.pdf. Licence: CC BY 4.0. Retrieved 22 October 2026.
Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.