Commercial and tourism · 265-273 GEORGE STREET SYDNEY 2000 · Council of the City of Sydney · New South Wales
- Estimated development cost
- $75m
- To a 132 kV line
- 0.2 km
Overview
Development application to Council of the City of Sydney for commercial development, office premise, alterations or additions to an existing building or structure.
- Location
- 265-273 GEORGE STREET SYDNEY 2000, Council of the City of Sydney, New South Wales-33.8648, 151.2068
- Value
- $75m, estimated development cost
- Approving authority
- Central Sydney Planning Committee
- Distance to the grid
- 0.2 km to a 132 kV line. 1.9 km to 330 kV. 0.2 km to Dalley Street substation (132 kV).Straight line to operational lines and substations of 132 kV or more.
Approval progress
- Planning
- AssessmentLodged 15 May 2024
- ApprovedApproved 14 Nov 2024
- ConstructionNow
- Operating
- Development applicationNew South Wales · Central Sydney Planning Committee · D/2024/36715 May 2024 → 14 Nov 20245 monthsApproved
- Construction certificateNew South Wales · CFT-7770581 Sept 2025Certificate issued
Reports on this project
- Project brief, free.
- Project dossier, On enquiry.
- Insights report, On enquiry.
The facts on this page stay free.
What each contains© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the mapSite constraints
Site constraints
Checking national and NSW maps…
Comparable projects
- Modifications28 comparable projectsNone2.4 on average, half have 2 or fewer
Time to decision comes from the approval times benchmark. Condition counts are read from each consent's numbering.
Who's involved
- LipmanContractor, builder on the construction certificate
Nearby
- CBD MetroApproved0.2 km
- 301 and 305 Kent Street Concept Hotel DevelopmentApproved · $117m0.3 km
- Barangaroo - C2 Commercial & C6 KioskApproved · $32m0.4 km
- 4-6 Bligh Street HotelWithdrawn · $312m0.4 km
- Barangaroo - C4 Commercial Fit OutApproved · $128m0.4 km
- Barangaroo - Stage 1B BasementApproved · $234m0.5 km
Sources
- NSW Planning Portal, development applicationsDevelopment application D/2024/367 lodged with Council of the City of Sydney on 15 May 2024. Value: the estimated cost of development the applicant lodged. Shown as approved because a construction certificate followed at the same address. © State of New South Wales (Department of Planning, Housing and Infrastructure). Licence: CC BY 4.0. Retrieved 31 October 2026.
- NSW Planning Portal, construction certificates4 construction certificates issued from 1 September 2025 to 13 August 2026, the first CFT-777058. Builder named: Lipman Pty. Ltd. Matched to this project by claused. from the site address. © State of New South Wales (Department of Planning, Housing and Infrastructure). Licence: CC BY 4.0. Retrieved 25 November 2026.
- Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
Spotted an error? Tell us.
Get every change to commercial and tourism projects in NSW, and the firms you follow, in the Monday briefing.