Energy · Electricity supply

Central West Orana REZ Transmission – Wollar Substation Upgrade

WithdrawnEPBC: Controlled action, in assessment
Location
Barigan Rd, Wollar, Mid-Western Regional, New South Wales
Value
Not published
Owner
Not published
Contractors
Not named in a public source yet
State approval
Withdrawn
Federal approval (EPBC)
Controlled action, in assessment
Last activity
8 September 2021
See it on the map

Approvals

  • StateState significant infrastructure, SSI-27741480

    Withdrawn. NSW Department of Planning. Lodged 8 September 2021.

    View record
  • FederalEPBC Act referral, EPBC 2021/9055

    Controlled action, in assessment. Australian Government (DCCEEW).

    View record

Nearby projects

Sources

  1. EPBC Act referrals, Australian GovernmentLinked to this project by name and location. Licence: CC BY 4.0. Retrieved 20 October 2026.
  2. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 20 October 2026.

Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.