Batteries and pumped hydro · Energy

Calala Battery Energy Storage System

474 Calala Lane, Calala · Tamworth Regional · New South Wales

ApprovedSSD-52786213No EPBC referral1 modification
-31.1438, 150.9660Open the map
© OpenStreetMap · OpenMapTiles · OpenFreeMap

Where the approval stands

How this is worked out

Decided 18 months after its first record on the NSW portal. Of the 63 NSW generation and storage projects that entered the portal from August 2020 and have been decided, half took 34 months or less.

Decided, 18 months
Half of 63 comparable cases decided by Oct 2025
$518m
Capital investment value
18 mo
Time to decision
Typical 34 mo
170
Construction jobs
  • StateState significant development, SSD-52786213

    Approved. NSW Department of Planning. Lodged 19 December 2022. Decided 27 June 2024.

    View record

Constraints

Public maps, asked when this page opens · within 5 km

Checking national and NSW maps…

Facts and sources

Location
474 Calala Lane, Calala, Tamworth Regional, New South Wales
Owner
Not published
Contractors
Not named in a public source yet
Value
$518m, capital investment value
Jobs
170 during construction, 7 once operating
Last activity
12 June 2026
  1. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 22 October 2026.
  2. NSW Major Projects documentsCapital investment value stated in the Department's notice of decision, given as an approximate figure. Document: SSD Notice of Decision - Calala BESS.pdf. Licence: CC BY 4.0. Retrieved 22 October 2026.

Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.