Skip to content
Business Premises, 65 Martin Place Sydney
Commercial and tourism · 65 MARTIN PLACE SYDNEY 2000 · Council of the City of Sydney · New South Wales
- Estimated development cost
- $402m
- To a 132 kV line
- 0.2 km
Overview
Development application to Council of the City of Sydney for business premises, office premise, alterations or additions to an existing building or structure.
- Location
- 65 MARTIN PLACE SYDNEY 2000, Council of the City of Sydney, New South Wales-33.8682, 151.2117
- Value
- $402m, estimated development cost
- Approving authority
- Central Sydney Planning Committee
- Distance to the grid
- 0.2 km to a 132 kV line. 1.7 km to 330 kV. 0.7 km to Dalley Street substation (132 kV).Straight line to operational lines and substations of 132 kV or more.
Approval progress
- Planning
- AssessmentLodged 20 Nov 2025
- ApprovedApproved 19 Mar 2026
- ConstructionNow
- Operating
- Development applicationNew South Wales · Central Sydney Planning Committee · D/2025/116020 Nov 2025 → 19 Mar 20263 monthsApproved
- Construction certificateNew South Wales · CFT-99378517 Aug 2026Certificate issued
Reports on this project
- Project brief, free.
- Project dossier, On enquiry.
- Insights report, On enquiry.
The facts on this page stay free.
What each contains© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the mapSite constraints
Site constraints
Checking national and NSW maps…
Comparable projects
- Modifications28 comparable projectsNone2.4 on average, half have 2 or fewer
Time to decision comes from the approval times benchmark. Condition counts are read from each consent's numbering.
Who's involved
- BuiltContractor, builder on the construction certificate
Nearby
- Amending Stage 1 Concept Proposal (south site building envelope) Martin Place Station PrecinctApproved · $87m0.1 km
- 4-6 Bligh Street HotelWithdrawn · $312m0.3 km
- CBD MetroApproved0.7 km
- Australian Museum - Renewal ProjectApproved · $15m0.7 km
- 301 and 305 Kent Street Concept Hotel DevelopmentApproved · $117m0.9 km
- Mixed use development with affordable housing - 134 William St, WoolloomoolooIn planning0.9 km
Sources
- NSW Planning Portal, development applicationsDevelopment application D/2025/1160 lodged with Council of the City of Sydney on 20 November 2025. Value: the estimated cost of development the applicant lodged. Shown as approved because a construction certificate followed at the same address. © State of New South Wales (Department of Planning, Housing and Infrastructure). Licence: CC BY 4.0. Retrieved 31 October 2026.
- NSW Planning Portal, construction certificatesConstruction certificate CFT-993785 issued 17 August 2026. Builder named: Built Pty Limited. Matched to this project by claused. from the site address. © State of New South Wales (Department of Planning, Housing and Infrastructure). Licence: CC BY 4.0. Retrieved 25 November 2026.
- Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
Spotted an error? Tell us.