- $76m
- Capital investment value
- 2.4 km
- To a 132 kV line
- StateState significant development, SSD-49400708
Withdrawn. NSW Department of Planning. Lodged 16 October 2022.
View record
Constraints
Public maps, asked when this page opens · within 5 kmChecking national and NSW maps…
Facts and sources
- Location
- 1953-2109 Elizabeth Drive, Badgerys Creek, Penrith, New South Wales
- Owner
- Not published
- Contractors
- Not named in a public source yet
- Value
- $76m, capital investment value
- Distance to the grid
- 2.4 km to a 330 kV line. 6.9 km to Erskine Park substation (132 kV).Straight line from the mapped site to operational lines and substations of 132 kV or more.
- Last activity
- 16 October 2022
- NSW Major Projects documentsCapital investment value in the applicant's cost report. Document: _Appendix B - QS Report_.pdf. Retrieved 21 October 2026.
- NSW Major Projects portalLicence: CC BY 4.0. Retrieved 20 October 2026.
- Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.