Skip to content
WithdrawnSSD-6967 · No EPBC referral

Ardlethan Waste Facility

Waste and recycling · Tin Mine Road Ardlethan 2665 · Coolamon Shire · New South Wales

To a 132 kV line
52 km

Overview

Last activity 20 February 2019
Location
Tin Mine Road Ardlethan 2665, Coolamon Shire, New South Wales-34.3271, 146.8521
Value
Not published
Approving authority
NSW Department of PlanningDetermined by the Department of Planning, as the Minister's delegate
Distance to the grid
52 km to a 132 kV line. 70 km to 330 kV. 52 km to Yanco substation (132 kV).Straight line to operational lines and substations of 132 kV or more.
NSW portal case
SSD-6967First record 20 February 2019

Approval progress

1 approval on record
  1. Planning
  2. AssessmentLodged 20 Feb 2019
  3. WithdrawnDate not published
  • State significant developmentNew South Wales · NSW Department of Planning · SSD-6967
    20 Feb 2019 → date not published
    Withdrawn↗

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and NSW maps…

Comparable projects

Waste and recycling projects in New South Wales. Grey is the middle half of them, the marker is this project.
  • Modifications33 comparable projectsNone2.3 on average, half have 2 or fewer

Time to decision comes from the approval times benchmark. Condition counts are read from each consent's numbering.

  1. Yanco Solar FarmApproved · $99m52 km
  2. Comet Park Battery Energy Storage SystemIn assessment52 km
  3. Yanco Battery Energy Storage SystemApproved · $297m52 km
  4. Pace FarmApproved59 km
  5. Wyalong Solar FarmUnder construction · $130m64 km
  6. Devlins Bridge Wind FarmIn planning66 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 20 October 2026.
  2. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
  3. NSW Major Projects, case recordDetermination authority, portal stage and modification cases. Licence: CC BY 4.0. © State of New South Wales and Department of Planning, Housing and Infrastructure.

Spotted an error? Tell us.

Get every change to waste and recycling projects in NSW, and the firms you follow, in the Monday briefing.