Data centres · Water and utilities
43-61 Turner Road Data Centre
43-61 Turner Road, Gregory Hills · Camden · New South Wales
ApprovedSSD-68013714No EPBC referral1 modification
Where the approval stands
How this is worked outDecided 21 months after its first record on the NSW portal. Of the 446 NSW major projects that entered the portal from August 2020 and have been decided, half took 24 months or less.
Decided, 21 months
- $800m
- Capital investment value
- 21 mo
- Time to decision Typical 24 mo
- 100
- Construction jobs
- StateState significant development, SSD-68013714
Approved. NSW Department of Planning. Lodged 27 February 2024. Decided 20 November 2025.
View record
Constraints
Public maps, asked when this page opens · within 5 kmChecking national and NSW maps…
Facts and sources
- Location
- 43-61 Turner Road, Gregory Hills, Camden, New South Wales
- Owner
- Not published
- Contractors
- Not named in a public source yet
- Value
- $800m, capital investment value
- Jobs
- 100 during construction, 50 once operating
- Last activity
- 25 June 2026
- NSW Major Projects portalLicence: CC BY 4.0. Retrieved 21 October 2026.
- NSW Major Projects documentsCapital investment value stated in the Department's notice of decision. Document: SSD Notice of Decision.pdf. Licence: CC BY 4.0. Retrieved 21 October 2026.
Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.