Data centres · Water and utilities

43-61 Turner Road Data Centre

43-61 Turner Road, Gregory Hills · Camden · New South Wales

ApprovedSSD-68013714No EPBC referral1 modification
-34.0281, 150.7621Open the map
© OpenStreetMap · OpenMapTiles · OpenFreeMap

Where the approval stands

How this is worked out

Decided 21 months after its first record on the NSW portal. Of the 446 NSW major projects that entered the portal from August 2020 and have been decided, half took 24 months or less.

Decided, 21 months
Half of 446 comparable cases decided by Mar 2026
$800m
Capital investment value
21 mo
Time to decision
Typical 24 mo
100
Construction jobs
  • StateState significant development, SSD-68013714

    Approved. NSW Department of Planning. Lodged 27 February 2024. Decided 20 November 2025.

    View record

Constraints

Public maps, asked when this page opens · within 5 km

Checking national and NSW maps…

Facts and sources

Location
43-61 Turner Road, Gregory Hills, Camden, New South Wales
Owner
Not published
Contractors
Not named in a public source yet
Value
$800m, capital investment value
Jobs
100 during construction, 50 once operating
Last activity
25 June 2026
  1. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 21 October 2026.
  2. NSW Major Projects documentsCapital investment value stated in the Department's notice of decision. Document: SSD Notice of Decision.pdf. Licence: CC BY 4.0. Retrieved 21 October 2026.

Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.