Freight and logistics · Transport

Mod 8 - Impact of Fill

GPO Box 4073 Sydney New South Wales Australia 2001 · Fairfield · New South Wales

ApprovedNo EPBC referral1 modification
-33.8244, 150.8200Open the map
© OpenStreetMap · OpenMapTiles · OpenFreeMap

Where the approval stands

0.7 km
To a 132 kV line

No state or federal approval is recorded for this project yet.

Constraints

Public maps, asked when this page opens · within 5 km

Checking national and NSW maps…

Facts and sources

Location
GPO Box 4073 Sydney New South Wales Australia 2001, Fairfield, New South Wales
Owner
Not published
Contractors
Not named in a public source yet
Value
Not published
Distance to the grid
0.7 km to a 330 kV line. 1.2 km to Sydney West substation (330 kV).Straight line from the mapped site to operational lines and substations of 132 kV or more.
Last activity
13 August 2019
  1. NSW Major Projects portalKnown from its modification record. The original application is not on the portal. Licence: CC BY 4.0. Retrieved 22 October 2026.
  2. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.

Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.