The export adds the details for the controls you drew, behind the plan sheet. Each one is an original claused. drawing with construction notes, and names the published standard drawing it corresponds to.

Where a consent or council names a standard drawing, use that drawing. Blue Book, IECA and Catchments & Creeks drawings are copyright and are not reproduced here. Download them from the publisher and attach them in the export: they print in the set after the claused. details.
TD 01

Sediment fence

TYPICAL · NOT TO SCALE
SECTIONFLOWUPSLOPE, DISTURBED AREADOWNSLOPE600 TYP150SEDIMENT FENCE GEOTEXTILEON UPSLOPE FACE OF POSTSSTAR PICKET OR HARDWOOD STAKE1.5 m LONG, 2.5 m MAX CENTRESFABRIC TOE IN TRENCH,BACKFILLED AND COMPACTEDDRIVE POST FIRMLY INTOUNDISTURBED GROUNDPLANCONTOURFENCE ON THE CONTOUR,ENDS AND RETURNSTURNED UPSLOPEFLOW
SF Sediment fence
  1. Use below disturbed areas that shed sheet flow only. Do not place across a drainage line or use the fence to divert water.
  2. Run the fence along the contour. Turn each end upslope so water ponds behind the fence instead of escaping around it, and add returns to break long runs into short catchments.
  3. Excavate a trench 150 mm deep on the upslope side. Lay the fabric toe into the trench, backfill and compact over it.
  4. Drive star pickets or hardwood stakes on the downslope side of the trench at 2.5 m maximum centres. Fit safety caps to star pickets.
  5. Use woven or non-woven sediment fence geotextile, not shade cloth. Join lengths only at a post with a 150 mm overlap.
  6. Inspect daily and after rain. Remove sediment before it reaches half the exposed fabric height and repair any undercutting at once.
TD 02

Fibre roll or coir log

TYPICAL · NOT TO SCALE
SECTIONFLOWFIBRE ROLL OR COIR LOGSIZE AS SPECIFIEDTIMBER STAKE, SPACINGAS MANUFACTURER SPECIFIESSEAT ROLL IN SHALLOW TRENCHSO FLOW CANNOT PASS BENEATHSTABILISED OR VEGETATEDGROUND DOWNSLOPE
FR Fibre roll or sediment sock
  1. Use on batters, below small disturbed areas and at the toe of slopes where flow is sheet flow. Not a substitute for a sediment fence on long slopes.
  2. Lay rolls along the contour and seat each one in a shallow trench so water cannot pass beneath it.
  3. Butt or overlap the ends tightly and turn the end rolls upslope.
  4. Stake through or immediately downslope of the roll at the spacing the manufacturer specifies.
  5. Inspect after rain. Remove trapped sediment and replace rolls that have split or moved.
Check against, or replace with
TD 03

Diversion channel and bank

TYPICAL · NOT TO SCALE
SECTIONRUNOFFUPSLOPEWORK AREA (CWD) ORDISTURBED AREA (DWD)CHANNEL GRADED 1% TO 5%,ROUNDED OR TRAPEZOIDALLINE OR STABILISECOMPACTED EARTH BANK KEYED INTONATURAL GROUND. BANK AND CHANNELSIZED FOR THE DESIGN FLOWSTABILISE BANK AS SOONAS IT IS FORMED
CWD Clean water diversionDWD Dirty water diversion
  1. Clean water diversions (CWD) carry runoff from undisturbed land around the works to a stable outlet. Dirty water diversions (DWD) carry runoff from disturbed land to a sediment basin or trap.
  2. Grade the channel between 1% and 5% so it drains without scouring. Shape a rounded or trapezoidal channel, not a V.
  3. Build the bank from compacted fill, keyed into the ground. Size the channel and bank for the design flow shown in the plan.
  4. Line or stabilise the channel and bank as soon as they are formed. Use rock or a lining where velocities would scour bare soil.
  5. Discharge to a stable outlet. Never discharge clean water into a sediment basin or dirty water to a waterway.
  6. Inspect after rain and repair breaches, scour and sediment build-up.
TD 04

Rock check dam

TYPICAL · NOT TO SCALE
LONG SECTIONCREST OF DOWNSTREAM DAM LEVELWITH TOE OF UPSTREAM DAMFLOW400 MAXCROSS SECTIONCENTRE 150 MIN BELOW ENDSKEY 200 INTO BEDAND BANKSROCK 70 TO 150 NOMINALOR AGGREGATE BAGS
CD Check dam
  1. Use in channels and drains to slow flow and trap coarse sediment. Not for use in a live waterway without approval.
  2. Build with clean rock (nominally 70 mm to 150 mm), aggregate bags or another approved material, keyed 200 mm into the bed and banks.
  3. Keep the centre of each dam at least 150 mm lower than its ends so flow passes over the middle and not around the sides.
  4. Limit height to about 400 mm above the channel floor. Space the dams so the toe of each upstream dam is level with the crest of the next one down.
  5. Inspect after rain. Remove sediment before it reaches half the dam height and restore displaced rock.
TD 05

Stormwater inlet protection

TYPICAL · NOT TO SCALE
FIELD INLET: SECTIONFLOWFLOWGEOTEXTILE FILTERTOED IN 150POSTS AT ABOUT1 m CENTRESGRATED PITKERB INLET: PLANKERBLINTELROADGUTTER FLOWAGGREGATE BAGS, OVERFLOWGAP KEPT AT KERB ENDBAGS ANGLEDINTO KERB
IP Inlet protection
  1. Protect every inlet that can receive runoff from the works. Inlet protection is a last line of defence, not the primary sediment control.
  2. Field (drop) inlets: build a geotextile filter around the pit on posts at about 1 m centres with the fabric toed in, or ring the pit with aggregate bags.
  3. Kerb inlets: place aggregate bags across the approach so water ponds and drops its sediment before it reaches the lintel. Leave a gap so flow can still enter in heavy rain.
  4. Assess the flooding risk before blocking any inlet. Do not cover a grate with fabric unless water can still bypass it safely.
  5. Inspect daily and after rain. Remove sediment and replace torn fabric or split bags.
TD 06

Sediment basin

TYPICAL · NOT TO SCALE
SECTIONINFLOWSETTLING ZONEVOLUME PER SCHEDULESEDIMENT STORAGE ZONEVOLUME PER SCHEDULEMARKER POST: TOP OFSEDIMENT STORAGE ZONESTABILISED SPILLWAYCREST ABOVE SETTLING ZONECOMPACTEDEMBANKMENTFREEBOARDDEPTH
SB Sediment basin
  1. Size the basin for its catchment as scheduled on the plan: a settling zone of 10 × Cv × A × R plus a sediment storage zone, with Cv, A and R as stated in the basin calculations.
  2. Build the embankment from compacted fill keyed into natural ground. Strip topsoil and vegetation from the footprint first.
  3. Install a stabilised spillway sized for the design overflow, with its crest above the settling zone and freeboard to the top of the embankment.
  4. Mark the top of the sediment storage zone on a graduated post. Remove sediment when it reaches that mark.
  5. Treat (for example by flocculation) and test captured water before release. Discharge only when it meets the criterion in the approval, then restore the settling zone within five days of rain unless the approval says otherwise.
  6. Divert clean runoff away from the basin. Keep access for desilting plant.
TD 07

Excavated sediment trap

TYPICAL · NOT TO SCALE
SECTIONFLOWOVERFLOWBATTERS NO STEEPERTHAN 2H:1VROCK OR AGGREGATEOVERFLOW WEIRSEDIMENT STORAGE: CLEAN OUT AT HALF FULL
TR Sediment trap or sump
  1. Use for small catchments where a basin is not warranted, or at the outlet of a dirty water diversion before a basin is built.
  2. Excavate the trap with batters no steeper than 2H:1V and size it for the catchment and storage shown on the plan.
  3. Form a stabilised overflow weir of rock or aggregate at the outlet, set below the surrounding ground so overflow leaves at the weir only.
  4. Remove sediment once the trap is half full. Inspect after rain.
Check against, or replace with
TD 08

Stabilised site access

TYPICAL · NOT TO SCALE
SECTION200 MINCLEAN ROCK 40 TO 70 NOMINALGEOTEXTILE ONCOMPACTED SUBGRADEPLANROADSEDIMENT FENCE15 m MIN OR TO BUILDING LINE3 m MINHUMP DIRECTS RUNOFF TOSEDIMENT FENCE OR TRAP
SSA Stabilised site access
  1. Make every vehicle exit from the site through a stabilised access. Restrict other exits.
  2. Strip topsoil, level and compact the subgrade and cover it with geotextile.
  3. Place a pad of clean rock (nominally 40 mm to 70 mm) at least 200 mm thick, at least 3 m wide and at least 15 m long or to the building line.
  4. Form a hump or shallow bund across the pad so runoff from it is directed to a sediment fence or trap, not to the road.
  5. Add a shaker grid or wash bay where soil still tracks onto the road. Sweep (do not hose) sediment from the road at the end of each day.
  6. Top up or replace the rock when it fills with soil.
TD 09

Stockpile

TYPICAL · NOT TO SCALE
SECTIONFLOWDIVERSION BANKOR CHANNEL UPSLOPESTABILISE OR COVER IF IN PLACE MORE THAN 10 DAYSSEDIMENT FENCE (TD 01)OR SEEDED BUND1 TO 2 m2 m MAX21CLEAR OF DRAINAGE LINES BY THE DISTANCE ON THE PLAN
SP Stockpile
  1. Place stockpiles inside the sediment controls and clear of drainage lines, waterways, kerbs, roads and vegetation by the distance stated on the plan.
  2. Form low, elongated stockpiles on the contour with batters no steeper than 2H:1V. Keep topsoil stockpiles below 2 m high.
  3. Divert upslope runoff around the stockpile with a bank or channel.
  4. Install a sediment fence or a compacted and seeded bund 1 m to 2 m downslope.
  5. Cover or stabilise any stockpile that will stand for more than 10 days.
Check against, or replace with
TD 10

Surface stabilisation

TYPICAL · NOT TO SCALE
BATTER SECTIONEROSION CONTROL BLANKET, PINNED,TOP EDGE BURIED IN A TRENCHSEED, FERTILISE ANDMULCH 50 TO 70 THICKTOPSOIL 75 (FLATTER THAN 4:1)40 TO 60 (STEEPER THAN 4:1)TURF IN FLOW PATHS
ST Stabilised area
  1. Stabilise disturbed areas progressively and as soon as each area reaches final level.
  2. Rip or scarify compacted ground along the contour before spreading topsoil. Respread topsoil about 75 mm deep on slopes flatter than 4H:1V and 40 mm to 60 mm on steeper slopes. Slopes steeper than 2H:1V need specialist treatment.
  3. Seed and fertilise, then cover with mulch 50 mm to 70 mm thick, or with an erosion control blanket pinned to the manufacturer's pattern with the top edge buried in a trench.
  4. Use turf in concentrated flow paths, kerb strips and where immediate cover is needed.
  5. Water and maintain cover until at least 70% ground cover is established, or the cover the approval requires.
TD 11

Exclusion fencing and limit of disturbance

TYPICAL · NOT TO SCALE
ELEVATIONNO GO ZONENO ENTRY, NO STOCKPILINGAT REGULAR SPACINGPICKET WITH SAFETY CAPHIGH-VISIBILITY MESH OR BUNTING
NG No go zoneLOD Limit of disturbance
  1. Fence no go zones (retained vegetation, waterway buffers, heritage items) before any clearing, and keep the fence in place until the works are complete.
  2. Mark the limit of disturbance with fencing or highly visible flagging before clearing. Do not disturb, stockpile or park plant beyond it.
  3. Use star pickets with safety caps or temporary fence panels carrying high-visibility mesh or bunting.
  4. Fix signs reading NO GO ZONE at intervals along the fence and at every likely entry point.
Your dataPlans and worksheets stay in your browser unless you sign in to save them to your account, ask for a review, or download the set as a PDF.A review sends a summary of the plan's controls, measurements, notes and calculations, not the map or your files, for processing by Anthropic's Claude. We do not store the summary. The review it returns is saved with your plan.Download PDF sends the finished sheets, with their map and drawing images, to our server in Sydney to be made into one PDF. We do not store them.