The export adds the details for the controls you drew, behind the plan sheet. Each one is an original claused. drawing with construction notes, and names the published standard drawing it corresponds to.
Where a consent or council names a standard drawing, use that drawing. Blue Book, IECA and Catchments & Creeks drawings are copyright and are not reproduced here. Download them from the publisher and attach them in the export: they print in the set after the claused. details.
TD 01
Sediment fence
TYPICAL · NOT TO SCALE
SF Sediment fence
Use below disturbed areas that shed sheet flow only. Do not place across a drainage line or use the fence to divert water.
Run the fence along the contour. Turn each end upslope so water ponds behind the fence instead of escaping around it, and add returns to break long runs into short catchments.
Excavate a trench 150 mm deep on the upslope side. Lay the fabric toe into the trench, backfill and compact over it.
Drive star pickets or hardwood stakes on the downslope side of the trench at 2.5 m maximum centres. Fit safety caps to star pickets.
Use woven or non-woven sediment fence geotextile, not shade cloth. Join lengths only at a post with a 150 mm overlap.
Inspect daily and after rain. Remove sediment before it reaches half the exposed fabric height and repair any undercutting at once.
CWD Clean water diversionDWD Dirty water diversion
Clean water diversions (CWD) carry runoff from undisturbed land around the works to a stable outlet. Dirty water diversions (DWD) carry runoff from disturbed land to a sediment basin or trap.
Grade the channel between 1% and 5% so it drains without scouring. Shape a rounded or trapezoidal channel, not a V.
Build the bank from compacted fill, keyed into the ground. Size the channel and bank for the design flow shown in the plan.
Line or stabilise the channel and bank as soon as they are formed. Use rock or a lining where velocities would scour bare soil.
Discharge to a stable outlet. Never discharge clean water into a sediment basin or dirty water to a waterway.
Inspect after rain and repair breaches, scour and sediment build-up.
Protect every inlet that can receive runoff from the works. Inlet protection is a last line of defence, not the primary sediment control.
Field (drop) inlets: build a geotextile filter around the pit on posts at about 1 m centres with the fabric toed in, or ring the pit with aggregate bags.
Kerb inlets: place aggregate bags across the approach so water ponds and drops its sediment before it reaches the lintel. Leave a gap so flow can still enter in heavy rain.
Assess the flooding risk before blocking any inlet. Do not cover a grate with fabric unless water can still bypass it safely.
Inspect daily and after rain. Remove sediment and replace torn fabric or split bags.
Size the basin for its catchment as scheduled on the plan: a settling zone of 10 × Cv × A × R plus a sediment storage zone, with Cv, A and R as stated in the basin calculations.
Build the embankment from compacted fill keyed into natural ground. Strip topsoil and vegetation from the footprint first.
Install a stabilised spillway sized for the design overflow, with its crest above the settling zone and freeboard to the top of the embankment.
Mark the top of the sediment storage zone on a graduated post. Remove sediment when it reaches that mark.
Treat (for example by flocculation) and test captured water before release. Discharge only when it meets the criterion in the approval, then restore the settling zone within five days of rain unless the approval says otherwise.
Divert clean runoff away from the basin. Keep access for desilting plant.
Stabilise disturbed areas progressively and as soon as each area reaches final level.
Rip or scarify compacted ground along the contour before spreading topsoil. Respread topsoil about 75 mm deep on slopes flatter than 4H:1V and 40 mm to 60 mm on steeper slopes. Slopes steeper than 2H:1V need specialist treatment.
Seed and fertilise, then cover with mulch 50 mm to 70 mm thick, or with an erosion control blanket pinned to the manufacturer's pattern with the top edge buried in a trench.
Use turf in concentrated flow paths, kerb strips and where immediate cover is needed.
Water and maintain cover until at least 70% ground cover is established, or the cover the approval requires.
Fence no go zones (retained vegetation, waterway buffers, heritage items) before any clearing, and keep the fence in place until the works are complete.
Mark the limit of disturbance with fencing or highly visible flagging before clearing. Do not disturb, stockpile or park plant beyond it.
Use star pickets with safety caps or temporary fence panels carrying high-visibility mesh or bunting.
Fix signs reading NO GO ZONE at intervals along the fence and at every likely entry point.